Actions
Feature #101
open[M10] Notification Engine (Basic) — 60% complete
Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/17/2026
Due date:
% Done:
60%
Estimated time:
Description
Gantt progress snapshot (17 Aug 2026)¶
- Module: M10 Notification Engine (Basic)
- Phase: Phase 1 MVP (W10–W12)
- Percent complete: 8%
- Percent remaining: 92%
Done in TeamTalks today¶
Email OTP via SMTP (console fallback).
Still to do¶
Assessment scheduled/reminder/submission/result email & SMS, WhatsApp, push notifications.
Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.
Updated by Ayush Yadav on 08/24/2026 12:10 PM
- % Done changed from 8 to 55
Phase 1 W14 catch-up shipped: session auth, tests/attempts, CBT autosave, server scoring, reports, Razorpay stub, descriptive scoring.
Updated by Ayush Yadav on 08/25/2026 06:34 AM
- Subject changed from [M10] Notification Engine (Basic) — 8% complete to [M10] Notification Engine (Basic) — 60% complete
- % Done changed from 55 to 60
Actions