Feature #99

open

[M8] Reports & Analytics (Basic) — 70% complete

Added by Ayush Yadav on 08/17/2026 10:55 AM. Updated on 08/25/2026 06:34 AM.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/17/2026
Due date:
% Done:

70%

Estimated time:

Description

Gantt progress snapshot (17 Aug 2026)

  • Module: M8 Reports & Analytics (Basic)
  • Phase: Phase 1 MVP (W10–W12)
  • Percent complete: 5%
  • Percent remaining: 95%

Done in TeamTalks today

Hardcoded admin analytics placeholders; JoSAA Rank Predictor (not attempt analytics).

Still to do

Score/rank/percentile from real attempts, time-per-question, topic strength/weakness, institution comparative reports.

Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.

Actions #1

Updated by Ayush Yadav on 08/24/2026 12:10 PM

  • % Done changed from 5 to 60

Phase 1 W14 catch-up shipped: session auth, tests/attempts, CBT autosave, server scoring, reports, Razorpay stub, descriptive scoring.

Actions #2

Updated by Ayush Yadav on 08/25/2026 06:34 AM

  • Subject changed from [M8] Reports & Analytics (Basic) — 5% complete to [M8] Reports & Analytics (Basic) — 70% complete
  • % Done changed from 60 to 70

Progress update (25 Aug 2026)

  • Percent complete: 70%

Done

  • Attempt report: score, max, accuracy, time, rank, percentile, topic insights, section times
  • Admin Reports panel + GET /reports/attempts/{id}
  • Candidate result screen after submit

Still to do

Institution comparative reports, PDF/Excel export, historical improvement trends.