Feature #106
open[M15] White Label Portal — 0% complete
Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/17/2026
Due date:
% Done:
0%
Estimated time:
Description
Gantt progress snapshot (17 Aug 2026)¶
- Module: M15 White Label Portal
- Phase: Phase 2 (W17–W20)
- Percent complete: 0%
- Percent remaining: 100%
Done in TeamTalks today¶
Nothing implemented.
Still to do¶
Custom branding/domain, email templates/certificates, white-label admin panel.
Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.