Feature #110

open

[M19] Large-Scale Exam Delivery — 5% complete

Added by Ayush Yadav on 08/17/2026 10:55 AM. Updated on 08/25/2026 06:34 AM.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/17/2026
Due date:
% Done:

5%

Estimated time:

Description

Gantt progress snapshot (17 Aug 2026)

  • Module: M19 Large-Scale Exam Delivery
  • Phase: Phase 3 (W24–W28)
  • Percent complete: 0%
  • Percent remaining: 100%

Done in TeamTalks today

Docker Compose MySQL only.

Still to do

10k concurrent load test, Redis + CDN, AWS/Azure autoscaling, offline mode + sync.

Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.