Feature #91

open

[OVERVIEW] TeamTalks vs AceZone Gantt — overall status — 28% complete

Added by Ayush Yadav on 08/17/2026 10:55 AM. Updated on 08/25/2026 06:34 AM.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/17/2026
Due date:
% Done:

28%

Estimated time:

Description

Gantt progress snapshot (17 Aug 2026)

  • Module: OVERVIEW TeamTalks vs AceZone Gantt — overall status
  • Phase: Overview (W1–W48)
  • Percent complete: 9%
  • Percent remaining: 91%

Done in TeamTalks today

Email auth, candidate profile, 6 exam-bank schemas, CAT 10,092 Q JSON, Ollama MCQ generate, CBT UI shell, grammar LMS.

Still to do

Finish Phase 1 MVP (~15% today): CBT wiring, server scoring, test authoring, payments, institution, reports, notifications. Then Phase 2–3 and remaining banks.

Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.

Actions #1

Updated by Ayush Yadav on 08/24/2026 12:10 PM

  • % Done changed from 9 to 70

Phase 1 W14 catch-up shipped: session auth, tests/attempts, CBT autosave, server scoring, reports, Razorpay stub, descriptive scoring.

Actions #2

Updated by Ayush Yadav on 08/25/2026 06:34 AM

  • Subject changed from [OVERVIEW] TeamTalks vs AceZone Gantt — overall status — 9% complete to [OVERVIEW] TeamTalks vs AceZone Gantt — overall status — 28% complete
  • % Done changed from 70 to 28

Progress update (25 Aug 2026)

  • Percent complete: 28% (was 9% on the original Gantt snapshot; Phase 1 MVP is ~60%)
  • GitLab ayush_yadav / main c5a13f5
  • Redmine wiki published: [[Wiki]], [[Architecture]], [[Progress]]

Now in the product

  • Session-authenticated mutating APIs (X-Session-Token)
  • Live tests / attempts / server scoring / examiner scoring
  • Practice home wired to published mocks and bank samples
  • Razorpay stub + assessment email on publish/submit
  • Default Super Admin kingayush2001@gmail.com

Still to do

Finish remaining Phase 1 gaps (real PSP, SMS/WhatsApp, full institution isolation), then Phase 2–3 and Gantt-scale banks.