Gantt progress snapshot (17 Aug 2026)¶
- Module: M5 Auto Evaluation Engine
- Phase: Phase 1 MVP (W8–W11)
- Percent complete: 8%
- Percent remaining: 92%
Done in TeamTalks today¶
Client-side MCQ scoring in Practice and syllabus assessments.
Still to do¶
Server grading, negative/partial/bonus marks, formula/range tolerance, hybrid auto+manual.
Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.
Updated by Ayush Yadav on 08/24/2026 12:10 PM
- % Done changed from 8 to 65
Phase 1 W14 catch-up shipped: session auth, tests/attempts, CBT autosave, server scoring, reports, Razorpay stub, descriptive scoring.
Updated by Ayush Yadav on 08/25/2026 06:34 AM
- Subject changed from [M5] Auto Evaluation Engine — 8% complete to [M5] Auto Evaluation Engine — 75% complete
- % Done changed from 65 to 75
Progress update (25 Aug 2026)¶
- Percent complete: 75%
Done¶
- Server-side objective grading in
AssessmentService(MCQ / multi / T-F / numerical) - Marks + negative marks from the bank item
- Hybrid: objective auto-scored, DESCRIPTIVE left for examiner
Still to do¶
Partial/bonus schemes, formula/range tolerance, more numerical parsers.