Feature #97

open

[M6] Descriptive Evaluation System — 50% complete

Added by Ayush Yadav on 08/17/2026 10:55 AM. Updated on 08/25/2026 06:34 AM.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/17/2026
Due date:
% Done:

50%

Estimated time:

Description

Gantt progress snapshot (17 Aug 2026)

  • Module: M6 Descriptive Evaluation System
  • Phase: Phase 1 MVP (W8–W12)
  • Percent complete: 0%
  • Percent remaining: 100%

Done in TeamTalks today

Nothing implemented.

Still to do

Rich-text + file upload, handwritten sheets, rubric UI, double evaluation, moderation workflow.

Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.

Actions #1

Updated by Ayush Yadav on 08/24/2026 12:10 PM

  • % Done changed from 0 to 40

Phase 1 W14 catch-up shipped: session auth, tests/attempts, CBT autosave, server scoring, reports, Razorpay stub, descriptive scoring.

Actions #2

Updated by Ayush Yadav on 08/25/2026 06:34 AM

  • Subject changed from [M6] Descriptive Evaluation System — 0% complete to [M6] Descriptive Evaluation System — 50% complete
  • % Done changed from 40 to 50

Progress update (25 Aug 2026)

  • Percent complete: 50%

Done

  • DESCRIPTIVE question type persisted on exam-bank items
  • Candidate textarea in Practice
  • Examiner panel: PUT /attempts/{id}/manual-score then recompute totals

Still to do

Rich-text + file upload, handwritten sheets, rubric UI, double evaluation, moderation.