Gantt progress snapshot (17 Aug 2026)

  • Module: M3 Assessment Authoring Engine
  • Phase: Phase 1 MVP (W4–W8)
  • Percent complete: 15%
  • Percent remaining: 85%

Done in TeamTalks today

Admin add-question API, Ollama generate into banks, exam/subject catalog seeder.

Still to do

Real test entity, faculty question picker, scheduling/slots, section config, delivery modes. Admin Create Mock Test is a fake toast.

Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.

Actions #1

Updated by Ayush Yadav on 08/24/2026 12:10 PM

  • % Done changed from 15 to 70

Phase 1 W14 catch-up shipped: session auth, tests/attempts, CBT autosave, server scoring, reports, Razorpay stub, descriptive scoring.

Actions #2

Updated by Ayush Yadav on 08/25/2026 06:34 AM

  • Subject changed from [M3] Assessment Authoring Engine — 15% complete to [M3] Assessment Authoring Engine — 80% complete
  • % Done changed from 70 to 80

Progress update (25 Aug 2026)

  • Percent complete: 80%

Done

  • Real assessment_tests entity with sections, question picker from banks, schedule window, PUBLIC/PRIVATE, paid flag
  • Admin Test authoring panel: create, pick questions, publish/unpublish
  • Publish triggers assessment-scheduled email when SMTP is configured

Still to do

Richer delivery modes, slot capacity, faculty review/approval workflow.