Feature #94
open[M3] Assessment Authoring Engine — 80% complete
Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/17/2026
Due date:
% Done:
80%
Estimated time:
Description
Gantt progress snapshot (17 Aug 2026)¶
- Module: M3 Assessment Authoring Engine
- Phase: Phase 1 MVP (W4–W8)
- Percent complete: 15%
- Percent remaining: 85%
Done in TeamTalks today¶
Admin add-question API, Ollama generate into banks, exam/subject catalog seeder.
Still to do¶
Real test entity, faculty question picker, scheduling/slots, section config, delivery modes. Admin Create Mock Test is a fake toast.
Source: AceZone_Assessment_Engine_Gantt_Chart.xlsx scored against the TeamTalks React + Spring Boot repo. Overall product is ~9% complete (~91% remaining). Phase 1 MVP is ~15% complete.